Solar Power Park Scheme: Central Government Expands Clean Energy Initiative
Solar Power Park Scheme: Central Government Expands Clean Energy Initiative
NEW DELHI Solar Power Park Scheme
The Union government plans to launch the second phase (solar power park scheme) of a dedicated program to develop solar parks across the country that will aim to plug loopholes and overcome slow progress.
Two officials with knowledge of the matter said the expanded scheme would seek to address the issue of solar park developers failing to make initial investments and delaying the development of projects till they receive money from power producers who place bids to develop power in such projects. The government is also looking to address the issue of inflated detailed project reports (DPR), they said.
According to one of the officials, “The people who come for developing solar parks, they don’t put in any money. They first do the bids for power developers. The money which comes from bids, they develop the solar parks.”
The scheme, which is known as ‘Development of Solar Parks and Ultra Mega Solar Power Projects’, was launched in December 2014 to help solar project developers set up projects in a plug-and-play model. The scheme is valid till the end of this fiscal. The government now plans to launch the second phase of this scheme with a focus on floating solar projects.
“We are thinking of expanding the scheme and coming up with a second part, particularly to take care of floating solar parks. The cost is higher in floating solar parks. Subsidy rates will be better,” the second official said. The focus on floating solar parks will reduce the need for vast stretches of land to set up similar parks.
However, the technology for floating solar module projects, wherein photovoltaic solar panels are mounted on floating structures on water bodies, is expensive. Under the current scheme, the MNRE provides central financial assistance (CFA) of up to ₹20 lakh per MW or 30% of the project cost, including grid-connectivity cost, whichever is lower. The solar parks are developed in partnerships with state governments and their agencies, CPSUs, and private entrepreneurs.
The implementing agency is termed as a solar power park developer (SPPD). Post the selection of the SPPD, bids are sought for power developers, which are largely independent power producers (IPP) to produce power at the site in a plug-and-play model.
On the instances of SPPDs lagging in infrastructure development, Amit Kumar, partner, and leader for Power, Utilities and Mining, PwC India said: “The scheme is aimed at providing a plug-and-play model of infrastructure for the power developers, but the opposite happens in some instances where the SPPD starts development of the project only after the money comes in from the IPPs. This delays the project.”
Further, according to sector experts, project development is delayed even if the SPPDs receive a grant from the Centre for the project.
Suggested Articles

PM Surya Ghar Muft Bijli Yojana 2025: Online Registration Made Simple
PM Surya Ghar Muft Bijli Yojana 2025: Learn how to register online and get free electricity under this government scheme.

Solar for Metal & Fabrication Units: Cost, Benefits and Installation in India
A practical guide on solar for metal and fabrication units in India covering installation cost, benefits, system options, and the installation process.

Solar Roof Hook Installation: Step-by-Step Guide
A step-by-step guide to solar roof hook installation, covering positioning, alignment, and best practices for strong and reliable rooftop systems.

Can Solar Systems Support Industrial Motors and Machines? A Complete Guide
Discover how using solar for heavy machines can power industrial equipment reliably and cost-effectively for greener operations.

Solar Net Metering in Industrial Units: Opportunities and Risks
Solar net metering can help factories save on energy costs, but there are key pitfalls to consider. Learn the challenges and best practices for industrial adoption

Civil Structural General Arrangement (GA) Drawing in Solar Projects: Complete Design & Layout Guide
A Civil Structural General Arrangement (GA) drawing in solar projects is a detailed layout that defines the placement of solar modules, mounting structures, inverters, and civil foundations. It plays a crucial role in ensuring accurate design, optimal space utilization, and smooth execution of both rooftop and ground-mounted solar installations. This guide explains the key components, design considerations, and best practices for creating effective GA drawings in solar EPC projects.

Solar for Food Processing Units: Cost, Benefits, Installation & ROI in India
A complete guide on solar systems for the FMCG industry in India covering installation cost, benefits, ROI, system sizing, and the installation process.

Safe Handling of Solar PV Components: Complete Guide for EPC & Installers
Proper material handling is crucial in solar PV projects to avoid damage, reduce losses, and ensure safety. This guide covers best practices for transporting, storing, and installing solar components efficiently.